Precautions for ringlock scaffold support system use:
1.It is strictly prohibited to stack any overweight materials on the ringlock scaffold.
2.The height of the operation on the ringlock scaffold can be limited to normal operation range, and it is prohibited to add any ultra-high objects on the ringlock scaffold in any way.
3.The operator shall not be free to remove the basic components of scaffolding, tube, connectors, protective measures, etc. If the temporary demolition is necessary for operation, it must be dismantled by professionals after the consent of the technical department, and be strengthened accordingly according to the requirements, and restored after the completion of the operation.
4.Before each construction operation , the ringlock scaffolding in the construction area must be carefully checked, and the problems found should be put forward in time, and the hidden dangers should be eliminated by professionals. After confirming that there are no safety hazards, the construction operation can continue.
5.After the completion of the ringlock scaffolding work every day, the movable objects on the ringlock scaffolding board‘s surface must be cleaned to prevent the moving objects from falling.